当前学科:信息系统项目管理师(高级)
  • 题目: 单选题
    The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

      Aestimating

      Bdefining

      Cplanning

      Dsequencing

    答案: <查看本题扣1积分>

    查看答案

    答案不对?请尝试站内搜索