    ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.

      AQuantitative Risk Analysis

      BQualitative Risk Analysis

      CEnterprise Environmental Factors

      DRisk Management Plan