当前学科:系统集成项目管理工程师(中级)
  • 题目: 单选题
    The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

      Aestimating

      Bdefining

      Cplanning

      Dsequencing

    答案: <查看本题扣1积分>

    查看答案

    答案不对?请尝试站内搜索


推荐知识点: