  • 题目: 单选
    The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.

      A . A、project work breakdown
      B . B、project security authentication
      C . C、project management
      D . D、project flowchart

    答案: <查看本题扣1积分>