  • 题目: 单选题
    Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.

      Aanalyze

      Btrack

      Clevel

      Dextend

    答案: <查看本题扣1积分>

    查看答案