当前学科:信息系统项目管理师(高级)
  • 题目: 单选题
    In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.

      A10

      B45

      C50

      D100

    答案: <查看本题扣1积分>

    查看答案

    答案不对?请尝试站内搜索