  • 题目: 单选题
    On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.

      Atime estimating

      Bcost estimating

      Cproject planning

      Dschedule development